This morning I was in St. Paul and stopped by the La Puerta Abierta Methodist church site. Work is moving along well there. The underground utilities have been installed, which required the removal of sidewalks and some street sections. The final patch work there was just being finished….

The plumbers are on site installing the underground building piping…..

While I was there I observed a large group of young people working on the community vegetable garden. They were busy weeding, tying up plants, turning compost bins, etc.

It was really nice to see these young folks so involved with a project like this.