100_3688 We have been busy the past few days at our dental clinic project in Prior Lake. The foundation for the addition has been completed, waterproofing and insulation installed, and backfilling completed. We can now navigate the site well and take on other tasks.

 

We started removing the exterior finishes on the100_3689 existing building. The building has and exterior comprised of cement stucco and brick masonry. We are removing the majority of that material. The substrate will be checked and repaired where necessary. We are installing new wind and water barriers on the wall. These were not available when the building was constructed and should help greatly with energy conservation and moisture protection.