Hospital Office Building, site work

We finished up the office building remodeling we were doing for the Northfield Hospital some time ago. The interior modifications were made and the exterior was repaired and painted. The building looks great now and should serve the hospital office functions well. Due to a very wet spring we were not able to move forward with much of...

Laura Baker Services, Baker Cottage

The majority of our work at Baker Cottage on the Laura Baker Services campus is completed. The exterior of the building has had the cement plaster finish applied. This building includes a yellow band....Ellwell has a blue band and Wright has a green band. I like the slight variation in colors for the buildings.  Retaining the brick ...

Northfield Historical Society

Our work at the Northfield Historical Soceity Scriver building is just about wrapped up. This has been a long project for us, in one of the tightest sites we have ever worked on. The work area was about 12' wide by 85' long. It fronted on the sidewalk along Bridge Square, had a building immediately to the west side, and a tiny, tiny ...

Neuger Communications

Last week we were busy installing drywall at the Neuger Communications office project. The steel framing has just about all been completed. Fortunately, we obtained our electrical inspection prior to the state government shutdown, so we were able to insulate walls and proceed with drywall work.  The offices and spaces are coming tog...

ArTech Charter School Expansion

Yesterday we started work on an expansion and remodeling for . ArTech is a K-12 charter school that has been operating in Northfield for a number of years. They are growing and successfully educating children---an need more space! So, we were selected to work with Peter Schmelzer of to create that new space. The work is not without ...

Open House at Historical Society

Last night the held an open  house for the public to see their newly completed renovations that we have been working on with them. The Scriver building never looked so proud! The Society provided snacks and beverages for people and let them wander around to inspect the new work. I had many comments from people about how wonderful e...

ArTech Expansion

We have been doing some work inside the ArTech school that we need to do for our remodeling work. With the heat last week it was good to be inside away from the sun. Late last week we did manage to get the site prepared where the expansion is going to be located. This involved excavating and hauling out organic soils and bringing in...

Neuger Communications…painting

The painters were busy last week doing painting work at the Neuger Communication project on Bridge Square. We finished up most of the drywall so they primed the walls. A big portion of the building is having the ceiling structure and mechanical ductwork exposed so they also painted that. The painters used what is called 'dryfall' pai...

ArTech Charter School Expansion

The last couple of weeks have been tough on us as we work on the ArTech Charter School expansion. It seems we have fought rain about every couple of days. And not just small amounts....we've had 2" and 3" rains wipe out our excavation work twice. But, the past few days have been good and today we managed to place concrete for the bui...

ArTech School Expansion

We've had some great weather for our work at the ArTech charter school expansion project. Once the concrete floor was laid we moved right on to erecting the steel frame. This work always seems to move along rather quickly as we use machines to lift the beams and columns in place. As long as the setting bolt templates were prepared an...